Market Intelligence17 Nov 202610 min read

Frankfurt’s 300 MVA connection moves the risk downstream

Digital Realty’s dedicated 110 kV link at Fechenheim turns grid access into operating infrastructure—but 300 MVA is not 200 MW of live IT capacity.

Matthieu GallegoPowerlandMap
Frankfurt’s 300 MVA connection moves the risk downstream

Digital Realty’s new dedicated 110 kV connection at Digital Park Fechenheim changes the status of one of Frankfurt’s largest data-centre campuses. The important change is not that the campus has announced more capacity. It is that a physical power route, built over roughly 20 months and at a stated triple-digit-million-euro cost, is now operational.

That removes a major external dependency from the next phases. It does not make 300 MVA of connection capacity equivalent to 200 MW of commissioned IT load, and it does not establish how much space or power customers can contract today. For customers, lenders and competitors, the project should therefore be read as a shift from grid-access risk to campus-delivery risk.

My view is that this is the right way to assess Frankfurt’s next expansion cycle. A large connection is valuable because it makes later buildings more credible. The commercial value is realised only when internal electrical systems, data halls, cooling, permits and customer contracts convert that connection into usable IT capacity.

What changed on 17 November

Digital Realty’s 17 November announcement says the fully underground link runs approximately 16 kilometres from the Karben substation to Digital Park Fechenheim. The company owns the connection and describes it as capable of providing up to 300 MVA of grid-connection capacity.

The same release describes a long-term campus plan comprising 11 data centres and up to 200 MW of IT capacity. Three facilities are operating. A fourth is planned for 2027. Digital Realty does not say that all 200 MW is commissioned, contracted or available now.

Those figures belong to different layers of the project and should remain separate.

Disclosed itemFigure or statusWhat it provesWhat it does not prove
Grid voltage110 kVHigh-voltage connection architectureCustomer-ready capacity
Connection ratingUp to 300 MVAApparent-power ceiling of the dedicated route300 MW IT or 300 MW of deliverable customer load
RouteAbout 16 km undergroundA completed physical link from KarbenInternal distribution completed for every future building
Delivery periodRoughly 20 monthsConstruction and commissioning of the connectionThe development timetable for all 11 facilities
InvestmentTriple-digit millions of eurosMaterial capital committed to power infrastructureExact cost, return or cost per delivered MW
Campus planUp to 200 MW IT across 11 data centresFull-build design ambitionCurrent commissioned or available IT MW
Current facilitiesThree operatingExisting operational campus activityThe capacity or occupancy of each building
Next facilityFourth planned for 2027A near-term development milestoneA guaranteed customer handover date

This separation matters because the market often treats the largest number in a release as the project’s capacity. Here, the largest number is an electrical connection rating expressed in MVA. The commercial product is IT power, normally expressed in MW, delivered inside specific buildings under defined redundancy and cooling conditions.

The 300 MVA figure gives a boundary, not a conversion

MVA measures apparent power. Converting it to active electrical power requires a power factor. Converting electrical input into usable IT load then requires assumptions about cooling, electrical losses, mechanical systems, lighting and other facility consumption. None of those assumptions is disclosed in the announcement.

An illustrative calculation shows why the distinction matters. At a power factor of 0.95, a 300 MVA connection would correspond to an active-power boundary of 285 MW before considering the site’s operating configuration. If a fully developed 200 MW IT campus operated at a PUE of 1.25, it would require around 250 MW of facility input. The implied difference would be 35 MW against the 285 MW illustration.

That is not a forecast for Fechenheim. It is a sensitivity test:

Illustrative casePower factorPUEFacility input for 200 MW ITDifference from active-power boundary
Efficient case1.001.20240 MW60 MW
Base illustration0.951.25250 MW35 MW
Higher-overhead case0.951.35270 MW15 MW

The formula is straightforward: active-power boundary equals MVA multiplied by power factor, while facility input equals IT MW multiplied by PUE. The result changes materially with operating assumptions. It also ignores redundancy, reserve margins, phased energisation and any contractual limits imposed by the utility or campus network.

The useful conclusion is not that the connection is oversized or undersized. It is that the disclosed 300 MVA and 200 MW IT figures are directionally compatible under plausible scenarios, while the actual deliverable capacity still depends on building-level engineering and contracts.

Frankfurt has a documentation problem as well as a power problem

PowerlandMap’s public, verified German supply records currently contain 308 published project or facility records. Sixty-eight are in Frankfurt am Main. All 68 have a verified public source, but only 21 disclose an IT-capacity figure. Those 21 records sum to 626.1 MW IT.

That total is a documentation measure, not an estimate of Frankfurt’s complete market capacity. It includes records at different stages and scopes, and it should not be used as a live-supply figure. Forty-seven Frankfurt records still lack a source-supported IT MW value. Unknown is not zero.

The Digital Realty subset shows the same limitation. PowerlandMap currently has 23 public Frankfurt records associated with Digital Realty, but only one—FRA20—contains a separately disclosed IT figure, at 16 MW. The other facility pages establish locations, building specifications and operating status without consistently publishing site-level IT capacity.

This creates a practical gap between campus-scale announcements and procurement decisions. A customer evaluating a 5 MW or 10 MW deployment does not need only the campus ceiling. It needs to know which building can deliver the load, on what date, with what electrical topology, cooling design, reservation status and expansion rights.

The new connection improves the credibility of those conversations. It does not replace them.

Owning the grid connection changes the campus economics

Digital Realty’s decision to develop a dedicated connection is strategically important because it brings part of the power-delivery chain inside the campus investment case. Instead of relying solely on a standard connection whose expansion timing may be shared with other users, the operator has funded and delivered a specific high-voltage asset.

That can create three advantages.

First, it gives future buildings a clearer route to power. The campus still needs internal works, but the upstream route has moved from plan to operating infrastructure.

Second, it improves phasing. An 11-building campus can align substations, data halls and customer commitments against a common connection rather than negotiate each building as a standalone grid project.

Third, it may strengthen financing. Lenders and investors can distinguish between a parcel with a connection promise and a campus with an operational high-voltage route. The latter still carries construction and leasing risk, but one of the most difficult external milestones has been completed.

The counter-argument is that dedicated infrastructure concentrates capital and utilisation risk. A triple-digit-million-euro connection earns its return only if subsequent buildings and customer deployments arrive on schedule. If demand is slower, the owner carries the cost of underused infrastructure. If internal construction or permitting slips, an operational grid asset can wait ahead of the revenue-producing data halls it was built to serve.

That is why the next facility matters more than the headline ratio. The fourth data centre, planned for 2027, will show whether the campus can convert the new connection into a repeatable delivery cadence.

The competitive test moves from access to execution

Frankfurt remains Germany’s most established data-centre cluster, but grid constraints have pushed operators to look beyond the traditional core and to pursue more complex power solutions. Recent projects include dedicated high-voltage connections, larger suburban campuses and, in some cases, proposed on-site generation.

Fechenheim offers a different signal from a new market announcement. The campus already has operating facilities, a multi-building plan and now an energised connection. Competitors cannot answer that simply by announcing land or a target MW figure. They need to show comparable evidence: permits, contracted power, physical grid works, internal energisation and a dated building handover.

For customers, the decision should therefore be staged. I would not ask whether Fechenheim “has 300 MVA available”. I would ask:

1. Which building and phase can deliver the required IT load? 2. How much of the connection is allocated, reserved and physically energised behind that building? 3. What PUE and redundancy assumptions define the quoted IT MW? 4. Which cooling system supports the intended rack density? 5. What milestone converts the 2027 plan into a contractual ready-for-service date?

Those questions turn the connection from a marketing number into a procurement input.

What to verify next

The first milestone is the fourth facility. Digital Realty’s 2027 plan should be tested against construction status, internal substation readiness, cooling design and a building-specific handover date.

The second is allocation. The market needs a clearer bridge between 300 MVA at the connection, 200 MW IT at full build and the capacity assigned to individual facilities. That bridge should identify current load, contracted load, reserve margin and future phases without treating all four as the same thing.

The third is utilisation. Customer contracts, commissioning evidence and building-level availability will determine whether the connection supports revenue growth at the pace implied by the campus plan.

The fourth is the wider Frankfurt response. A successful sequence at Fechenheim would strengthen the case for operators to invest directly in high-voltage routes where standard connection timelines cannot support their development programmes. It would also raise the entry threshold: land and a grid application would look less competitive beside a campus that has already financed and commissioned its connection.

Digital Park Fechenheim has therefore crossed an important boundary. It is no longer waiting for its main upstream power route to become real. The risk has moved downstream, into the buildings, contracts and operating systems that must turn that route into usable IT capacity.

That is progress, but it is not completion. In a constrained market, the winning campus will be the one that can prove the entire chain—from high-voltage connection to customer rack—at the date and scale promised.

*Analysis by Matthieu Gallego, PowerlandMap. PowerlandMap record counts were checked on 17 November 2026. The sensitivity cases are illustrative and do not represent Digital Realty operating data or forecasts.*