Switzerland’s Bulle project makes heat recovery a delivery contract

Infomaniak and Gruyère Energie’s 2.5 MW project in Bulle shows why useful data-centre heat depends on an energy offtaker, liquid cooling and contracts—not a headline recovery rate.

Matthieu GallegoPowerlandMap
Switzerland’s Bulle project makes heat recovery a delivery contract

Switzerland’s next regional data-centre project is small enough to inspect in detail and ambitious enough to expose a much larger market question: when does recovered server heat become infrastructure rather than a sustainability claim?

On 13 November 2026, Infomaniak said that the planning application for a new data centre in Bulle, in the canton of Fribourg, had entered public display. The project is being developed with Gruyère Energie, whose district-heating network runs beside the site. Infomaniak plans 2.5 MW of IT capacity, around 170 racks and a building footprint of roughly 1,200 square metres. Construction could begin in the first half of 2027, subject to permits, with commissioning planned for 2028.

The headline is the intended recovery of all server heat. The commercial point is more demanding: the data centre, heat pumps, district network and customer demand must operate as one system. Bulle therefore matters less as a record-sized facility than as a test of whether a sovereign cloud operator and a local utility can turn a continuous thermal by-product into contracted, useful energy.

The project starts with 2.5 MW of IT load—not 28 GWh of guaranteed output

The units need to remain separate. Infomaniak describes 2.5 MW as planned IT capacity, not grid connection capacity and not a measured operating load. At full load and normal operation, the company expects the servers’ electricity consumption to produce roughly the same continuous amount of heat before the heat pumps. Gruyère Energie estimates that the system could then deliver about 28 GWh of heat a year to its network, after the heat pumps.

Those figures describe different parts of the energy chain. The 2.5 MW figure belongs to the IT estate. The 28 GWh figure is an annual thermal-delivery estimate after temperature uplift. Neither is evidence of heat already sold or delivered. The project is still in permitting, and the parties said that their agreements remain to be finalised.

That distinction is strategically important. A data centre can recover heat inside its fence without creating an economic asset. Value appears only when there is a nearby network, sufficient demand across the year, equipment able to raise the temperature efficiently, and a contract allocating investment and operating risk.

The Infomaniak announcement gives Bulle an unusually clear starting specification. Storage servers would use air cooling connected to a closed water loop. Compute and AI servers would use direct liquid cooling, capturing heat closer to the chips and at a higher temperature. Gruyère Energie’s heat pumps would then raise that temperature for the district network. Infomaniak says that the cooling system would not withdraw water once its closed loops are filled.

Heat recovery is an offtake problem

Bulle’s strongest advantage is not a novel heat exchanger. It is the location of an operating district-heating network immediately beside the planned building.

Gruyère Energie says that its network is supplied by more than 95% renewable energy and aims to deliver 180 GWh of heat by 2030. The proposed data centre’s 28 GWh annual contribution would equal about 15.6% of that target if both figures were achieved on the stated basis. That ratio is a useful measure of scale, but not a forecast of fossil-fuel displacement: the network is already largely renewable, demand will evolve, and the data-centre estimate depends on actual IT utilisation and heat-pump performance.

This changes the investment question. In a greenfield location without a heat network, the data-centre operator may face the cost of pipes, pumping, heat pumps and customer conversion while still carrying demand risk. In Bulle, an established utility owns the relationship with the thermal network and already has a growth plan. The connection distance is limited because the network passes the plot. That can lower civil works and reduce one of the main uncertainties in heat-reuse projects.

It does not remove contractual risk. The parties still need to decide who finances and owns the heat pumps, who pays for electricity used by them, how availability is measured, what happens during maintenance, how heat is priced and who bears the risk if the data-centre load ramps more slowly than expected. These details will determine whether “100% recovery” becomes a bankable service or remains an engineering capability.

Liquid cooling changes both compute density and heat quality

The Bulle design also links artificial-intelligence infrastructure to the economics of district heating.

High-density compute produces concentrated thermal loads that are increasingly difficult to manage with air alone. Direct liquid cooling can remove heat at a higher temperature because the coolant is close to the processors. For the operator, this supports denser GPU and compute deployments. For the utility, higher-temperature recovered heat can reduce the temperature lift required from heat pumps and therefore the electricity needed per unit of useful heat.

That is the strategic connection: the same investment that prepares the facility for next-generation compute can improve the conditions for heat reuse. The cooling architecture is not merely an environmental add-on. It can influence rack density, available capacity, heat-pump efficiency and the revenue or avoided-cost case for the energy partner.

The limits matter just as much. “Liquid-cooled” does not establish the inlet temperature, return temperature, flow rate, redundancy design or coefficient of performance of the heat pumps. Infomaniak has not disclosed those values for Bulle. The 28 GWh estimate should therefore remain a project forecast until operating data confirms delivered heat, electricity consumed by the heat pumps and seasonal availability.

A phased, self-financed project changes the risk profile

Infomaniak plans to finance the project from cash generated by its activities and to invest in phases. The company reported a 26.5% increase in service billings in the first half of 2026. That context supports the expansion case, but it does not reveal the project’s capital expenditure, utilisation schedule or customer commitments.

Phasing can protect returns in a regional market. Racks, electrical equipment and cooling capacity can be installed as cloud and AI demand materialises rather than all at once. It can also align the heat supply ramp with growth in Gruyère Energie’s network. The trade-off is that the thermal system must remain efficient across partial loads, not only at the full-load condition used for the annual heat estimate.

This is where the sovereign-cloud strategy becomes relevant. Infomaniak is not building a wholesale shell for an unnamed tenant. It expects to operate its own infrastructure for storage, public cloud and AI services under Swiss law. That gives it more control over workload placement and deployment timing, but also leaves demand risk with the operator. The project’s success will depend on converting cloud-service growth into sustained IT load at Bulle.

What PowerlandMap’s Swiss data shows—and what it does not

PowerlandMap currently records 57 published Swiss data-centre supply entries across 30 cities, with 12 active pipeline records. Only eight of those records have a verified or published IT-capacity figure, totalling 135.3 MW IT. That is a record-level total for the disclosed subset, not a national market denominator; most Swiss facilities do not publish comparable IT capacity.

The closest useful Infomaniak benchmark in the current dataset is D4 in Plan-les-Ouates. PowerlandMap records D4 as operational with 1.5 MW IT. Its separate 1.7 MW heat-output figure is thermal capacity and must not be added to IT MW. Infomaniak describes Bulle as twice D4’s capacity, while separately stating 2.5 MW IT for the new project. Those statements may reflect different design or operating bases, so PowerlandMap will preserve the direct figures and avoid forcing a false equivalence.

Bulle has not yet been canonicalised as a supply record in the platform. The announcement and the municipal filing provide a strong candidate, but the facility should enter the inventory with its planning status, stated IT basis, site identity and sources intact—not as an operating asset. The City of Bulle public-inquiry record identifies Infomaniak Network SA, the Chemin du Stand site, parcels 850 and 597, case 2026-3-00767-O, and an inquiry period running from 13 November to 14 December 2026.

This is the kind of project where status discipline matters. A public display is not a permit. A planned heat-recovery system is not delivered heat. A commissioning target is not an operating date.

The counterargument: recovered heat is not automatically the best heat

A serious objection is that data-centre heat may be technically recoverable but economically secondary in a network already supplied by more than 95% renewable energy. The value is not necessarily a simple carbon comparison with heating oil. It may instead come from diversifying local heat supply, supporting network expansion, avoiding other generation investment, or improving the utilisation of infrastructure already being built.

The network also has to absorb a relatively constant source while customer demand varies by season and hour. Thermal storage, alternative heat sources and dispatch rules may be needed. Maintenance or an IT outage can interrupt the source. Conversely, a warm period or slower building connection programme can reduce useful demand even when the servers are running.

The project’s quoted avoidance of up to 7,500 tonnes of CO₂ and 2.8 million litres of heating oil is a counterfactual supplied by the project partners. It should be tested against the actual marginal heat source displaced in Gruyère Energie’s network, not treated as an operating result.

These are not reasons to dismiss Bulle. They are the reasons to watch its contracts and operating evidence closely. The strongest heat-reuse projects are those that publish the boundary conditions behind the headline percentage.

What should investors and customers watch next?

Five milestones will decide whether Bulle becomes a repeatable model.

First is the permitting process. The municipal inquiry runs through 14 December 2026, after which objections, conditions and approvals will shape the schedule. Second is the final agreement between Infomaniak and Gruyère Energie, including ownership of the heat pumps and the commercial treatment of delivered heat. Third is a confirmed construction start in the first half of 2027.

Fourth is the deployment plan: disclosed phases, rack density, power availability and the balance between storage and liquid-cooled compute. Fifth is operating evidence after the planned 2028 commissioning—actual IT load, PUE, water use, heat-pump electricity, delivered GWh, seasonal utilisation and network availability.

For customers, the project offers a clearer connection between Swiss data sovereignty, regional compute capacity and local energy infrastructure. For investors and developers, it shows that heat recovery is most credible when site selection starts with an offtaker and a network, not when a pipe is added after the data centre has been designed.

Bulle’s 2.5 MW will not transform the European capacity map. It could, however, improve the way smaller sovereign-cloud projects are evaluated. The decisive metric will not be the percentage of heat that can be captured inside the building. It will be the amount of heat contractually accepted, efficiently upgraded and verifiably delivered to customers over time.

*Analysis by Matthieu Gallego, PowerlandMap.*

View the discussion on LinkedIn